Construction of a gas pipeline connecting the offshore pipeline with the National Transmission System
- high pressure gas pipeline
- diameter: 900 i 1000 mm
- MOP: 8,4 MPa
- lenght: about 41 km
- The investment has been completed.
-
pipeline section from the first weld connecting the offshore gas pipeline with the onshore gas pipeline to and including the Niechorze Valve Station (length of approx. 90 m),
- DN 900 pipeline section from the Niechorze Valve Station to the Receiving Terminal in Konarzewo, municipalities of Rewal, Karnice (length approx. 4.5 km),
- Receiving Terminal in Konarzewo,
- the DN 1000 pipeline section from the Receiving Terminal to the Płoty Transmission Network Point, municipalities of Karnice, Trzebiatów, Gryfice, Płoty (length approx. 36.5 km), together with the reconstruction of the Płoty Point.
Furthermore, the completion of the Baltic Pipe, of which this project makes part, strengthen Poland’s energy security. The construction of new transmission infrastructure will also stimulate the development of the gas market and its competitiveness.
The municipalities where the project was implemented will get a substantial benefit in the form of revenue from the property tax to be paid annually by GAZ-SYSTEM.
- Engineering Contractor: A consortium of: PGNiG Gazoprojekt S.A. and ILF Consulting Engineers Polska Sp. z o.o.
- Investor’s Supervision Contractor: SGS Polska sp. z o.o
- Building Contractor: consortium of UAB MT Group (Leader) and PPS Pipeline Systems GmbH
The project was implemented on the basis of the provisions of the Act of 24 April 2009 on investments in regasification terminal for liquefied natural gas in Świnoujście (for consolidated text see Journal of Laws of 2021, item 1836).
While implementing its investment projects GAZ-SYSTEM S.A. respects the rights of all interested stakeholders. We encourage you to send comments and questions concerning the project which has been granted the PCI using the Form for questions and comments concerning the implementation of projects with PCI status by GAZ- SYSTEM.
Environmental consultations
On February 8, 2019, the Regional Director for Environmental Protection in Szczecin announced the initiation of proceedings to issue a decision on environmental conditions for the development of “Investment into infrastructure required for the operation of the international gas pipeline (known as Baltic Pipe) connecting the transmission systems of the Republic of Poland and the Kingdom of Denmark – the onshore part.
On March 6, 2019, the Regional Director for Environmental Protection in Szczecin published a notice on the initiation of proceedings in respect of an environmental impact assessment for the project named “Investment into infrastructure required for the operation of the international gas pipeline (known as Baltic Pipe) connecting the transmission systems of the Republic of Poland and the Kingdom of Denmark- the onshore part”, as part of the proceedings aimed at issuing a decision on environmental conditions for the development of the above-mentioned project.
Environmental decision
On May 17, 2019, the Regional Director of Environmental Protection in Szczecin issued a decision on environmental conditions for the project executed by GAZ-SYSTEM named “An investment project constituting infrastructure required for the operation of international gas pipeline (known as Baltic Pipe) connecting the transmission systems of the Republic of Poland and the Kingdom of Denmark – the onshore part”.
Location decision
On June 21, 2019, the Zachodniopomorski Voivode signed a decision on the location for the “Construction of infrastructure required for the operation of the international gas pipeline (known as Baltic Pipe) connecting the transmission systems of the Republic of Poland and the Kingdom of Denmark”. The project will consist of the engineering design, construction and operation of a DN1000 gas pipeline from the Płoty Network Point to the Goleniów Compressor Station, together with the upgrading of the Płoty Network Point.
The process of obtaining location decisions continued between June and September 2019 and ultimately led to the issuance of three separate decisions for the following sections: Niechorze – Płoty, Płoty – Goleniów and Wilczkowo Block Valve Station. All three decisions are final.
Building permit
On February 4, 2020, the Zachodniopomorski Voivode issued two decisions granting building permits for the gas pipeline connecting the offshore gas pipeline with the national transmission, concerning the following scopes:
- the construction of the Receiving Terminal in Konarzewo, including access road and water supply line;
- the upgrading of the Płoty Transmission Network Point.
On March 10, 2020, the Zachodniopomorski Voivode issued another building permit decision for the gas pipeline connecting the offshore gas pipeline with the national transmission system in the scope of:
On March 19 and 20, 2020, the Zachodniopomorski Voivode issued the last two decisions granting building permits for the gas pipeline connecting the offshore gas pipeline with the national transmission, concerning the following scopes:
Konsorcjum PGNiG Gazoprojekt S.A. i ILF Consulting Engineers Polska Sp. z o.o.
ILF Consulting Engineers Polska Sp. z o.o.
ul. Osmańska 12
02–823 Warszawa
phone number. +48 22 430 26 00
e-mail: info.waw@ilf.com
PGNiG GAZOPROJEKT S.A.
ul. Strzegomska 55a
53-611 Wrocław
phone number. (71) 785 11 00
e-mail: sekretariat@gazoprojekt.pl
Wykonawca Nadzoru Inwestorskiego:
SGS Polska Sp. z o.o.
ul. Ignacego Daszyńskiego 7
72-320 Trzebiatów
phone number. +48 691767469
Contract Manager:
Andrzej Kończak
phone number. 609 601 517
Wykonawca Robót Budowlanych:
Konsorcjum firm UAB MT Group (Lider) i PPS Pipeline Systems GmbH.
UAB MT Group | PPS Pipeline Systems GmbH
Kareiviu 6
LT-09117 Wilno
Litwa
PPS Pipeline Systems GmbH
Marszalkowska 126/134
00-008 Warschau
Polen
Construction office:
Prusinowo 1,
72-300 Prusinowo Gmina Gryfice
Real estate expert:
Wojciech Skulski
tel. 601 480 631
Dorota Jędrzejczyk
phone number. 605 298 808
Real estate and communication expert:
Julia Kufel
phone number. 721 121 812, 733 197 251
Inwestor:
Gas Transmission Operator GAZ-SYSTEM S.A.
Oddział w Poznaniu
ul. Grobla 15
61-859 Poznań
phone number. +48 61 854 45 03
e-mail: komunikacja.poznan@gaz-system.pl