Pogórska Wola – Tworzeń
- high pressure gas pipeline, diameter: 1000 mm
- operating pressure: 8.4 MPa, length: approx. 168 km
Project status:
- Gas pipeline construction completed
- in November 2021, the final acceptance of Sections I and II took place, and in July 2022, the final acceptance of Section III.
Project route and location:
The gas pipeline route is divided into three sections:
- Section I: Pogórska Wola-Pałecznica, length approx. 78 km
- Section II: Pałecznica-Braciejówka, length approx. 56 km
- Section III: Braciejówka-Tworzeń, length 34 km
The pipeline is located in the Lesser Poland, Świętokrzyskie and Silesian Voivodeships. Its route will cross the municipalities of: Skrzyszów, Tarnów, Lisia Góra, Dąbrowa Tarnowska, Żabno, Olesno, Gręboszów, Opatowiec, Bejsce, Kazimierza Wielka, Skalbmierz, Pałecznica, Radziemice, Słomniki, Iwanowice, Gołcza, Trzyciąż, Olkusz, Klucze, Bolesław, Sławków, Dąbrowa Górnicza.
The implementation of the investment project make it possible to:
- increase the transmission system capacity,
- enhance the attractiveness of land for new investment,
- strengthen the security of gas transportation in the region.
The amount of funding was PLN 616,608,593.21.
While implementing its investment projects GAZ-SYSTEM S.A. respects the rights of all interested stakeholders. We encourage you to send comments and questions concerning the project which has been granted the PCI using the Form for questions and comments concerning the implementation of projects with PCI status by GAZ- SYSTEM.
Environmental consultations
The Regional Director for Environmental Protection in Kraków announced the commencement of proceedings for the issuance of a decision on environmental conditions in respect of a project consisting in “The construction of a high pressure gas pipeline DN 1000, MOP 8,4 MPa from the Pogórska Wola compressor station to the Tworzeń network point within the scope of the construction of the Hermanowice - Strachocina - Pogórska Wola - Tworzeń - Twaróg - Odolanów gas pipeline, together with the infrastructure necessary for its operation in the Podkarpacie, Świętokrzyskie, Lesser Poland, Silesian, Opole and Greater Poland Voivodeships”.
The Notice of the Regional Director for Environmental Protection in Kraków is available under the link.
Environmental decision
On 28 December 2016, the Regional Director for Environmental Protection in Kraków issued Decision on environmental conditions for the investment consisting in the construction of a high-pressure gas pipeline DN 1000, MOP 8.4 MPa from the Pogórska Wola compressor station to the Tworzeń network point, within the scope of the construction of the Hermanowice - Strachocina - Pogórska Wola - Tworzeń - Twaróg - Odolanów gas pipeline, together with the infrastructure necessary for its operation in the Podkarpacie, Świętokrzyskie, Lesser Poland, Silesian, Opole and Greater Poland Voivodeships (decision ref. no. OO.4210.11.2016.JS)
The Notice of the Regional Director for Environmental Protection in Kraków is available under the link.
Decision on location
In respect of the Pogórska Wola - Tworzeń gas pipeline, the Świętokrzyskie Voivode (22.02.2017), the Silesian Voivode (13.03.2017) and the Lesser Poland Voivode (21.03.2017) issued decisions on the location.
- Notice of the Silesian Voivode on the issuance of a decision establishing the location for the investment project Pogórska Wola - Tworzeń – Task 4 (Sławków - Tworzeń section) – Notice IFXIII.747.3.2017 dated 15 March 2017
- Notice of the Lesser Poland Voivode on the issuance of a decision establishing the location for the investment project Pogórska Wola - Tworzeń – Task 1 (Pogórska Wola - Opatowiec section).
- Notice of the Lesser Poland Voivode on the issuance of a decision establishing the location for the investment project Pogórska Wola - Tworzeń – Task 3 (Pałecznica - Sławków section).
The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.
For more information about the compensation payments and construction process see the section For Landowners.
Antea Polska S.A.
ul. Dulęby 5
40-833 Katowice
phone number. 32 358 88 88
e-mail: pl@anteagroup.com
Building Contractor:
- Section I i II była firma Stalprofil S.A.
- Section III:
ul. Grzybowska 87
00-844 Warszawa
phone number. 22 378 88 80
e-mail: biuro@ids-bud.pl
Construction office:
ul. Laski 193,
41-303 Dąbrowa Górnicza
phone number. 607 171 577
e-mail: sekretariat.B197@ids-bud.pl
Investor’s Supervision Contractor:
SGS Polska Sp. z o.o.
Biuro Kontraktu
ul. Spółdzielcza 3, 32-300 Olkusz
phone number. 691 767 833
e-mail: pl.gs.tarnow@sgs.com
Investor:
Gas Transmission Operator GAZ-SYSTEM S.A.
Oddział w Świerklanach
ul. Wodzisławska 54, 44-266 Świerklany
phone number. 32 439 25 00
e-mail: komunikacja.swierklany@gaz-system.pl