Lewin Brzeski – Nysa

Gas pipeline construction
Key project parameters:
  • high pressure gas pipeline
  • diameter: 500 mm
  • operating pressure: 8.4 MPa
  • length: approx. 41 km
  • 14 km of branches with a diameter of DN 150/100

Investment status:
  • gas pipeline under engineering design

Location:

The project is located in Opolskie Voivodeship. The pipeline route runs mostly along the existing gas transmission pipeline through the area of ​​the communes: Lewin Brzeski, Niemodlin, Grodków, Skoroszyce, Pakosławice and Nysa.
Lewin Brzeski-Nysa gas pipeline map

Benefits

The new gas pipeline will replace the existing gas transmission pipeline and enable gas supplies to the developing economic zone in the Opolskie Voivodeship. The investment will also improve the capacity of the Polish natural gas transmission system and increase the economic importance of this part of southern Poland.

Administrative decisions

Environmental decision:
On 9 March, 2023, the Regional Director of Environmental Protection in Opole issued the decision (420.9.2022.AK.18) on the environmental conditions for the project named "Construction of gas pipeline DN 500; MOP 8,4MPa relation Lewin Brzeski - Nysa together with branches to SG - Lewin Brzeski; Skoroszyce; Grodków ul. Żeromskiego; Grodków ul. Warszawska".

Decision establishing the location:
On July 24, the Opolskie Voivode issued a decision marked IN.I.747.7.2023.AZ on establishing the location of the investment titled: "Construction of a DN500, MOP 8.4MPa gas pipeline from Lewin Brzeski to Nysa along with branches to Gas Stations - Lewin Brzeski; Skoroszyce; Grodków ul. Żeromskiego; Grodków ul. Warszawska."

Public consultations

GAZ-SYSTEM invites you to a public consultation on the Lewin Brzeski - Nysa gas pipeline project according to the following schedule:
Date Place of consultation Commune Precinct
06.06.2022
10:00 – 16:00
Urząd Miejski w Grodkowie
Sala nr 35 I piętro
ul. Warszawska 29
49-200 Grodków
Grodków Grodków, Głębocko, Kopice, Nowa Wieś Mała, Półwiosek, Więcmierzyce
09.06.2022
12:00 – 18:00
Pawilon Sportowy w Skoroszycach
ul. Braterstwa Broni 5
48-320 Skoroszyce
Skoroszyce Stary Grodków, Skoroszyce, Brzeziny, Makowice
Pakosławice Pakosławice, Prusinowice, Strobice
Nysa Hanuszów
10.06.2022
8:30 – 13:30
Urząd Miejski w Lewinie Brzeskim
Sala ślubów
ul. Rynek 1
49-340 Lewin Brzeski
Lewin Brzeski Buszyce, Kantorowice, Lewin Brzeski, Nowa Wieś Mała, Ptakowice 
Niemodlin Sarny Wielkie, Radoszowice, Tarnica
       
Detailed information about the consultations can be found on the poster.
 

Compensation payments

Under a special act regulating gas infrastructure projects, compensation payments are guaranteed to the owners of the land affected by the project development.

The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.

For more information about the compensation payments and construction process see the section For Landowners.

Contacts to Contractors and Investor

Design engineer:
ILF CONSULTING ENGINEERS POLSKA Sp. z o.o.
ul. Osmańska 12
02-823 Warszawa
phone number. 22 430 26 00
e-mail: info.waw@ilf.com

Investor:
Gas Transmission Operator GAZ‑SYSTEM S.A.
Oddział w Świerklanach
ul. Wodzisławska 54
44‑266 Świerklany
phone number. 32 439 25 00
e‑mail: komunikacja.swierklany@gaz-system.pl