Goleniów compressor station
- Capacity of the compressor station after expansion: 30 MW, of which Stage 1 – 25 MW and Stage - 5MW
- Stage 1 (25 MW – 2 x 10 MW compressors and 1 x 5 MW compressor) is implemented as part of the Baltic Pipe Project.
Investment status:
- The investment has been completed.
Location:
Investment was located in Goleniów municipality, Zachodniopomorskie Voivodeship
The role of the new Goleniów gas compressor station is provide incremental capacity of the transmission system by pumping additional volumes of gas from the Baltic Pipe offshore pipeline. It will strengthen Poland’s energy security and be a crucial link of the North-South Gas Corridor.
The municipality where the compressor station was upgraded will benefit significantly from the taxes to be paid annually by GAZ-SYSTEM.
The European Commission has granted the PCI (Project of Common Interest) status to the project. More information on the significance of the PCI status for the development of gas transmission infrastructure can be found in the dedicated section on PCI projects.
While implementing its investment projects GAZ-SYSTEM S.A. respects the rights of all interested parties. You are encouraged to send comments and questions concerning any project which was granted the PCI status using the Form for questions and comments concerning the implementation of projects with PCI status by GAZ- SYSTEM.
On June 26, 2019, the Governor of Zachodniopomorskie Voivodeship issued a location decision for the expansion of the Gas Compressor station in Goleniów. It is one of three such facilities on the Polish side of the Baltic Pipe project – the others being the Compressor Station in Odolanów, currently undergoing expansion, and the compressor station in Gustorzyn, which is a greenfield project.
The decision covers the implementation of the following investments:
- expansion of the Goleniów Compressor Station
- construction of a pig launcher/receiver station together with the necessary infrastructure for the DN1000 gas pipeline between Goleniów and Lwówek,
- construction of a pig launcher/receiver station together with the necessary infrastructure for the DN 1000 gas pipeline between the Płoty System Point and the Goleniów compressor station.
On January 28, 2020, the Governor of the Wielkopolskie Voivodeship issued a building permit for a terminal-related investment project comprising the expansion of the Goleniów Gas Compressor Station.
PGNiG GAZOPROJEKT S.A.
ul. Strzegomska 55a
53-611 Wrocław
phone number. (71) 785 11 00
e-mail: sekretariat@gazoprojekt.pl
Building Contractor:
MAX STREICHER S. P. A. .
Via Giovanni Keplero 5A
43122 Parma
Italy
Investor’s Supervision Contractor:
Eko-Inwest
ul. Jerzego Zimowskiego 20
71-281 Szczecin
phone number. 91 462 31 00
e-mail: biuro@eko-inwest.com.pl
Investor:
Gas Transmission System Operator GAZ-SYSTEM S.A.
Oddział w Poznaniu
ul. Grobla 15
phone number. +48 61 854 45 03
e-mail: komunikacja.poznan@gaz-system.pl