The construction of the gas pipeline is visible from a great height
Basic parameters and description of the project:
  • high pressure gas pipeline,
  • diameter: 1000 mm,
  • working pressure: 8,4 MPa,
  • length: approx. 154 km

Project status:
  • The construction of the Gustorzyn - Wronow gas pipeline was completed in 2023. 

Project route and location:
The pipeline is located in the Łódź, Mazovian and Lublin Voivodeships. The route pass through the territory of 15 municipalities: Rawa Mazowiecka; Regnów, Sadkowice; Mogielnica; Wyśmierzyce; Radzanów; Stara Błotnica; Jedlińsk; Głowaczów; Kozienice; Sieciechów; Gniewoszów; Żyrzyn; Puławy; Końskowola.Map showing the route of the Rawa Mazowiecka-Wronów gas pipeline
 

Benefits

The aim of the project was to build a high pressure gas pipeline from Gustorzyn to Leśniewice, which will enable the transmission of increased volumes of gas to Warsaw and Łódź agglomerations, Radom and its surroundings, and to the south-eastern regions of the country. The planned investment has also have an impact on the development of local infrastructure.

An important benefit for the local community is the property tax paid annually by GAZ-SYSTEM in the amount of up to 2% of the value of the transmission infrastructure under construction located in the territory of a given municipality. This amount is regular contribution to the local budget which may be spent on community needs.

Co-financing by the European Union

The construction of the gas pipeline received funding under Measure 11.2 Support for smart gas infrastructure for energy transition under Priority Axis XI of REACT-EU OPI&E 2014-2020.

Project of Common Interest (PCI)

The European Commission has granted the PCI (Project of Common Interest) status to the project. More information on the significance of the PCI status for the development of gas transmission infrastructure can be found in the  dedicated section on PCI projects.

While implementing its investment projects GAZ-SYSTEM S.A. respects the rights of all interested stakeholders. We encourage you to send comments and questions concerning the project which has been granted the PCI using the Form for questions and comments concerning the implementation of projects with PCI status by GAZ- SYSTEM.

Public consultations

Public consultations were organised in connection with the implementation of the project. The consultation events held to date and their schedule are presented below.

Administrative decisions

Environmental Decision:
On 8 June 2020, Regional Director for Environmental Protection in Warsaw issued a decision ref.: WOOŚ-II.420.379.2019.MP.34 on the environmental conditions for the project consisting in the construction of the Gustorzyn – Wronów gas pipeline Stage III Rawa Mazowiecka – Wronów

Decisions establishing the location:
  • Decision of Lubelski Voivode No. IF-II.747.13.2020 of 29 July, 2020
  • Decision of Łódzki Voivode No. 2/2020 of 17 August, 2020
  • Decision of Mazowiecki Voivode No. 92/SPEC/2020 of 31 August, 2020 (concerns the section from Mogielnica municipality to Stara Błotnica)
  • Decision of Mazowiecki Voivode No. 100/SPEC/2020 of 22 September, 2020 (concerns the section from Stara Błotnica municipality to Gniewoszów)
Building permit decisions:
  • Decision of Lubelski Voivode No. 65/21 of 4 June, 2020.(ref.: IF-I.7840.4.3.2021.KWW)
  • Decision of Łódzki Voivode No. 84/21 of 11 June, 2021
  • Decision of Mazowiecki Voivode No. 399/SAAB/2021 of 18 June, 2021 (concerns the section from Mogielnica municipality to Stara Błotnica)
  • Decision of Mazowiecki Voivode No. 400/SAAB/2021 of 18 June, 2021 (concerns the section from Stara Błotnica municipality to Gniewoszów)

Compensation payments

Under a special act regulating gas infrastructure projects, compensation payments are guaranteed to the owners of the land affected by the project development.

The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.

For more information about the compensation payments and construction process see the section For Landowners.

Contacts to Contractors and Investor

Design engineer was:
consortium ILF Consulting Engineers Polska Sp. z o.o. oraz PGNiG Gazoprojekt S.A.

Building Contractor:
Consortium ROMGOS Sp. z o.o. ENGINEERING Sp. k. oraz ROMGOS Gwiazdowscy Sp. z o.o
Biuro Budowy Gazociągu
ROMGOS Gwiazdowscy
Wsola, ul. Warszawska 31
26-660 Jedlińsk
phone number. 782 888 320
email: m.miller@romgos.pl   

Investor:
Gas Transmission Operator GAZ-SYSTEM S.A.
Oddział w Tarnowie
Pogórska Wola 450
33-152 Pogórska Wola
phone number. 14 622 53 00
e-mail: komunikacja.tarnow@gaz-system.pl