Kolnik-Gdańsk
Basic parameters and description of the project:
Project status:
Project route and location:
The pipeline will run through five municipalities in the Pomeranian Voivodeship including Gdańsk, Pruszcz Gdanski, Cedry Wielkie, Suchy Dąb and Pszczółki.
- high pressure gas pipeline,
- diameter: 1000 mm,
- operating pressure: 8.4 MPa,
- length: approx. 34 km.
Project status:
- Bidding procedures have been announced for the selection of contractors: construction works and investor supervision;
- Planned start date of preparatory and construction works Q1 2025;
- Planned completion date for construction work 2026. In late 2024/2025, after the selection of contractors and before the start of construction works, it is planned to organize informational meetings with the owners of the properties included in the investment and with residents. Details of the meetings will be published on the project website under the "Announcements" tab, through the Newsletter service and in the "Investment Guide" brochure. Those interested in receiving current information about the project through the Newsletter or by traditional mail are asked to contact komunikacja.gdansk@gaz-system.pl
Project route and location:
The pipeline will run through five municipalities in the Pomeranian Voivodeship including Gdańsk, Pruszcz Gdanski, Cedry Wielkie, Suchy Dąb and Pszczółki.
GAZ-SYSTEM invites you to informational meetings for the Kolnik-Gdansk:
Date | Place of meeting | Commune | Precinct | Information posters |
24.10.2024 r. 17:00-19:00 |
Szkoła Podstawowa nr 62, ul. Kępna 38; 80-638 Gdańsk Gdańsk | Gdańsk | Information poster |
The new pipeline will enable the off-take of additional gas volumes from the FSRU terminal located in the Gdańsk area. The investment will improve the capacity of the Polish transmission system and thus contribute to strengthening Poland's energy security.
The construction of new transmission infrastructure will also stimulate the development of the gas market and its competitiveness.
Local communities will gain an important benefit of the revenue from the property tax to be paid annually by GAZ-SYSTEM at the rate of 2% of the value of the transmission infrastructure section to be located in the territory of each municipality. This amount will be a regular contribution to the local budget which may be spent on community needs.
The construction of new transmission infrastructure will also stimulate the development of the gas market and its competitiveness.
Local communities will gain an important benefit of the revenue from the property tax to be paid annually by GAZ-SYSTEM at the rate of 2% of the value of the transmission infrastructure section to be located in the territory of each municipality. This amount will be a regular contribution to the local budget which may be spent on community needs.
The project is implemented on the basis of the provisions of the Act of 24 April 2009 on investments in regasification terminal for liquefied natural gas in Świnoujście (for consolidated text see Journal of Laws of 2024, item 551).
The European Commission has granted the PCI (Project of Common Interest) status to the project. More information on the significance of the PCI status for the development of gas transmission infrastructure can be found in the dedicated section on PCI projects.
While implementing its investment projects GAZ-SYSTEM S.A. respects the rights of all interested stakeholders. We encourage you to send comments and questions concerning the project which has been granted the PCI using the Form for questions and comments concerning the implementation of projects with PCI status by GAZ- SYSTEM.
While implementing its investment projects GAZ-SYSTEM S.A. respects the rights of all interested stakeholders. We encourage you to send comments and questions concerning the project which has been granted the PCI using the Form for questions and comments concerning the implementation of projects with PCI status by GAZ- SYSTEM.
A series of public consultation meetings were held in April and May 2021 for each commune along the route of the proposed gas pipeline.
Invitations to the meetings were sent both electronically and in printed form to the communes concerned, and through them to: village heads, local communities and owners of properties through which the project is to run.
The consultations were held in the form of one-on-one meetings with the residents (among other reasons due to epidemic restrictions), during which each participant could get to know the route of the planned gas pipeline and its course through their property. Representatives of the investor and the engineering company were also present and answered questions concerning, among other things, the safety of the infrastructure, compensation payments, legal basis for the project and timing of further works.
Within 7 days of the end of the consultations, each resident could express their reservations as to the route.
Invitations to the meetings were sent both electronically and in printed form to the communes concerned, and through them to: village heads, local communities and owners of properties through which the project is to run.
The consultations were held in the form of one-on-one meetings with the residents (among other reasons due to epidemic restrictions), during which each participant could get to know the route of the planned gas pipeline and its course through their property. Representatives of the investor and the engineering company were also present and answered questions concerning, among other things, the safety of the infrastructure, compensation payments, legal basis for the project and timing of further works.
Within 7 days of the end of the consultations, each resident could express their reservations as to the route.
- 23.04.2021 - Public consultations Kolnik-Gdańsk location: Juszkowo (PL)
- 26.04.2022 - Public consultations Kolnik-Gdańsk location: Cedry Wielkie (PL)
- 27.04.2021 - Public consultations Kolnik-Gdańsk location: Suchy Dąb (PL)
- 12.05.2021 - Public consultations Kolnik-Gdańsk location: Gdańsk (PL)
- 13.05.2021 - Public consultations Kolnik-Gdańsk location: Kolnik (PL)
Environmental decision:
- On 5 July 2021, the Regional Director for Environmental Protection in Gdańsk issued the first environmental decision (no. RDOŚ-Gd-WOO.420.67.2020.KSZ.32) for the approx. 1.2 km-long section of the Kolnik-Gdańsk gas pipeline.
- On 21 July 2021, the Regional Director for Environmental Protection in Gdańsk issued the second environmental decision (No. RDOŚ-Gd-WOO.420.59.2020.AJM/IK.39) for the remaining part of the Kolnik-Gdańsk gas pipeline.
- On 3 December 2021 Pomorskie Voivode issued a first decision on the location (no WI-III.747.1.19.2021.AM) for the onshore section of the Kolnik - Gdańsk gas pipeline connecting the floating terminal with the national transmission system.
- On 12 December 2021 Pomorskie Voivode issued a second decision on the location (no WI-III.747.1.23.2021.AM) for the remainder of the Kolnik - Gdańsk gas pipeline.
Building permit decision:
On 21.06.2022, a set of decisions approving construction designs and granting construction permits were obtained for the following investment tasks, among others:
On 21.06.2022, a set of decisions approving construction designs and granting construction permits were obtained for the following investment tasks, among others:
- Kolnik-Gdansk gas pipeline with a diameter of DN1000 and pressure of 8.4 MPa,
- high-pressure connection gas pipeline of the FSRU-Dry Weld Metering Station together with the metering station and fiber optic cable.
Under a special act regulating gas infrastructure projects, compensation payments are guaranteed to the owners of properties affected by the project development.
The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.
For more information about the compensation payments and construction process see the section For Landowners.
The compensation payment process is carried out in accordance with an administrative procedure, under the supervision of the competent Voivode. First, an independent expert is commissioned to carry out an assessment, which is the basis for determining the amount of compensation. Upon completion of the construction process, the Voivode issues an administrative decision specifying the amount of compensation due.
For more information about the compensation payments and construction process see the section For Landowners.
Hotline:
887 060 938
Design engineer:
Ramboll Polska Sp. z o.o.
ul. Bitwy Warszawskiej 1920 r. 7
02-366 Warszawa
phone number. 22 372 0050; 22 372 0054
e-mail: rpl-biuro@ramboll.com
Investor:
Gas Transmission Operator GAZ-SYSTEM S.A.
Oddział w Gdańsku
ul. Wałowa 47
80-858 Gdańsk
phone number. +48 58 744 05 00
e-mail: sekretariat.gdansk@gaz-system.pl
887 060 938
Design engineer:
Ramboll Polska Sp. z o.o.
ul. Bitwy Warszawskiej 1920 r. 7
02-366 Warszawa
phone number. 22 372 0050; 22 372 0054
e-mail: rpl-biuro@ramboll.com
Investor:
Gas Transmission Operator GAZ-SYSTEM S.A.
Oddział w Gdańsku
ul. Wałowa 47
80-858 Gdańsk
phone number. +48 58 744 05 00
e-mail: sekretariat.gdansk@gaz-system.pl
- Investment Guide No. 1 (PL)
- Investment Guide No. 2 (PL)
- Investment Guide No. 3 (PL)
- Investment Guide No. 4 (PL)
- Investment Guide No. 5 (PL)
- Brochure on the LNG FSRU Terminal in the Gdańsk area (PL)
- Brochure on the Kolnik – Gdansk gas pipeline (PL)
- Non-specialized description of the project Kolnik – Gdańsk (PL)