Skip to content
GAZ-SYSTEM Main site Logotyp BIP
  • Twitter
  • LinkedIn
  • YouTube
  • BlueSky
    • pl
  • About us
    • wróć do: Menu główne
    • About us
    • General
    • Regulatory environment
    • Announcements
    • Career
  • Transmission system
    • wróć do: Menu główne
    • Transmission system
    • NTS Map
    • SGT Map
    • Development of the system
    • Investment projects
    • Transmission infrastructure
    • For landowners
    • EU support
  • LNG Terminal
    • wróć do:
    • LNG Terminal
    • About LNG Terminal
    • Tariff and fee rates
    • Terminal Code
    • Application for services
    • Expansion Program
    • Documents for download
    • Technical data
    • Transparency Template
    • History of the investment
    • LNG at a glance
    • Secondary market
    • Consultation with market participants
  • For Customers
    • wróć do: Menu główne
    • For Customers
    • Amber Gas Corridor
    • Baltic Sea Gas Corridor
    • Transport routes across Poland
    • Biomethane
    • Services in the NTS
    • Services in the SGT
    • Provision of capacity
    • Laboratory services
    • Market information
    • Consult. market participants
    • Knowledge base
    • Gas calendar
  • For Suppliers
    • wróć do: Menu główne
    • For Suppliers
    • Tenders procedures
    • List of Reliable Suppliers
    • References
    • Our standards
    • Information package
  • For the Media
    • wróć do: Menu główne
    • For the Media
    • Press releases
    • Downloadable materials
    • Spokesperson
    • Annual report
  • ESG
    • wróć do: Menu główne
    • ESG
    • Ethics
    • Sponsorship
    • Donations
    • Natural Energy Fund
    • Educational support
    • Sustainability Report
  • Hydrogen market
    • wróć do: Menu główne
    • Hydrogen market
    • Hydrogen in a nutshell
    • Regulatory environment
    • Hydrogen market development
    • Projects
    • News
    • Contact
  • Contact
    • wróć do: Menu główne
    • Contact
    • For Stakeholders
    • Contact details
  • Twitter
  • LinkedIn
  • YouTube
  • BlueSky
  • GAZ-SYSTEM: Natural Gas, Pipelines
  • LNG Terminal
  • LNG Terminal - technical data
  • LNG Terminal
    • Information about LNG Terminal
    • Tariff and fee rates
      • LNG Calculator
      • Tariff computation methodology
    • LNG Terminal Code
    • Application for services
    • Expansion Program
    • For Download
    • Technical data
      • Ilość wyładowanego LNG
      • Awarie i ratownictwo
    • Transparency Template
      • Regulation (EC) No 2024/1789
    • History of the investment
    • LNG at a glance
    • Secondary market
    • Consultations with market participants
      • Current consultations
      • Completed market consultations
        • Consultation on changes to Terminal Code
        • Procedure for Offering the LNG Terminal

LNG Terminal - technical data

  • LNG Terminal
  • investment projects
  • EU co-financing

The LNG Terminal in Świnoujście is an installation designed for:

  • LNG unloading from carriers up to 217 000 m3 LNG
  • process storage in LNG tanks of the total capacity of 500 000 m3 LNG,
  • LNG regasification with the nominal annual capacity up to 8,3 bcm,
  • reloading LNG onto tank trucks,
  • reloading LNG onto small and large LNG carriers,
  • LNG bunkering.

Operational Data

  • Terminal capacity
  • Daily nominations
  • Daily renominations
  • Terminal unavailability
  • Actual quantity of unloaded LNG/truckloaded LNG

Annual schedule of works

The LNG Terminal Operator will publish the annual schedule of maintenance works which may affect the operating conditions of the LNG Terminal in Świnoujście, possibly restricting the provision of services such as regasification, loading tank trucks, LNG unloading and process storage.

Annual schedule of works in the Świnoujscie LNG Terminal for 2026

  
Date Limitation Planned Performed Additional information
April 21-22 2026 total limitation of the unloading capacities, total limitation of the reloading capacities and total limitation of the regasification capacities annual maintenance Done 110kV power station maintenence; electrical measurements,  XV/XXV valves check; HIPPS and XV07/XXV07 valves, SIF Tests
April 23 2026 total limitation of the unloading capacities, total limitation of the reloading capacities and partial limitation of the regasification capacities annual maintenance Done SIF tests,
EDG tests; 110 kV (No.3) Tests; HP pump performance test
May 12-15 2026 total limitation of the tank truck loading capacities Loading station annual maintenence Done  
 
June/July 2026 Unloading on Jetty2
Total limitation of transshipment capacities
annual maintenance Jetty1 Planned for May ’26 (W21-W22), moved to June-July June-July ’26 (W21-W22)T26-T27)
June 22 – July 3 2026
August/October 2026 partial limitation of the unloading capacities, total limitation of the reloading capacities, total limitation of bunkering capacities Jetty 2, valves maintenance Planned for June ’26, moved to August - October August – October ‘26
July 2026 Unloading on Jetty2
Total limitation of transshipment capacities
Hydraulic arms maintenance
Jetty1
Planned for July ’26 (W27-W28) Shall not be performed in 2026
September 2026 Unloading on Jetty1
Total limitation of reloading and transshipment capacities
annual maintenance Jetty2 (large scale) Gangway maintenance performed, other according to plan  September ’26 (W36-W37)
September 2026 Unloading on Jetty1
Total limitation of reloading and transshipment capacities
annual maintenance Jetty2 (small scale) Gangway maintenance performed, other according to plan  September ’26 (W38-W39)
October 2026 Unloading on Jestty1
Total limitation of reloading and transshipment capacities
Large and small scale arms tests.
ERS tests
  October ’26 (T41)

LNG Terminal Capacities

Information on the LNG Terminal available capacity presented below is for information purposes only, and shall not constitute an offer in the meaning of the Polish Civil Code Article 66 et seq.

Technical Capacity ot the LNG Facility

8,3 bcm/year

Technical regasification capacity

984 000 Nm3/h actual data
Nominal regasification capacity 946 000 Nm3/h
Contracted regasification capacity 946 000 Nm3/h actual data

Available regasification capacity*

0 Nm3/h actual data
Unloading capacity Jetty no. 1 12 000 m3 LNG/h
Unloading capacity Jetty no. 2 
quay 1
12 000 m3 LNG/h
Unloading capacity Jetty no. 2 
quay 2
1 000 m3 LNG/h
Loading capacity Jetty no. 2 
quay 1
4 000 m3 LNG/h
Loading capacity Jetty no. 2 
quay 2
1 000 m3 LNG/h
Transshipment capacity 10 000 m3 LNG/h
Loading capacity (trucks) 55 t LNG/h
Contracted loading capacity (trucks) 360 000 t LNG/y

Daily nominations and renominations

actual data

Actual quantity of regasified LNG

Terminal LNG point (ID 777001) gas flows

Quantity of LNG unloaded from tankers

actual data

Quantity of LNG transferred to trucks

actual data
Quantity of LNG transferred to ships actual data
Quantity of LNG bunkered actual data

Inventory of LNG in the tanks

actual data

* The regasification capacity resulting from the difference in gross calorific value can be available as a Separated Contracted Capacity.

Regasification method of the LNG

Regasification of the liquefied natural gas (LNG) in the LNG Terminal installation in Świnoujście consists in returning the fuel supplied in liquefied form into gaseous form by means of heating the liquefied fuel.

Regasification process is performed using so-called gas-heated submerged combustion vaporisers (SCV) in which the chilled LNG is heated. LNG is vaporised using water heated with boil-off gas, which then releases the heat onto the submerged tubes filled with flowing LNG.

The LNG consumption rate for the regasification process (so-called LCR in the Tariff for the LNG regasification service) is currently established at the level of 1,5 % of the quantity of LNG unloaded in the Świnoujście Terminal.

Additional LNG Truck Loading Capacity
Pursuant to Section 8.2.1 of the LNG Terminal Access Code for the Liquefied Natural Gas Terminal in Świnoujście, Operator Gazociągów Przesyłowych GAZ-SYSTEM S.A. hereby announces the availability of additional capacity of the LNG tank truck loading installation equivalent to up to 20 loading slots per Gas Day.

The additional capacity will be made available within the framework of the Tank Truck Loading Additional Service and allocated in accordance with the provisions of the LNG Terminal Access Code and the applicable Regasification Agreements.

In accordance with Sections 4.1.14, 8.1.1 and 8.2.2 of the LNG Terminal Access Code, only Terminal Users having a valid Regasification Agreement concluded with the Operator are entitled to apply for the allocation of Tank Truck Loading capacity, as Additional Services may be ordered exclusively by Terminal Users using Regasification Services.

Applications for the provision of the Tank Truck Loading Service (TT Application) will be processed on a first come, first served basis, subject to the availability of capacity and the technical capabilities of the Terminal. Capacity allocation will be confirmed by the Operator through the issuance of a TT Order, in accordance with the LNG Terminal Access Code. 
Applications should be submitted in accordance with the procedure set out in Section 8.2 of the LNG Terminal Access Code, using the applicable TT Application form and communication channels specified therein.

For detailed conditions of the Tank Truck Loading Service, Terminal Users are requested to refer to the LNG Terminal Access Code published on the Operator's website.
 

LNG Parameters

Quality parameters of LNG delivered to the Terminal shall meet the criteria indicated in the Terminal Code, point 6.8.

The quantity of LNG expressed in energy units (kWh) is established for reference conditions as per applicable ISO standard and Transmission Network Code (TNC), i.e.:

  • volume of gas at 0ºC (273.15 K)
  • gross calorific value at the temperature 25ºC (298.15 K),
  • pressure equal to ambient pressure of 101.325 kPa.
 

The content of other components in regasified LNG, such as hydrogen sulfide, total sulfur, mercaptan sulfur and mercury, must  comply with the provisions of TNC.

The LNG Terminal Operator shall ensure that the Gaseous Fuel generated in the LNG regasification process meets the criteria set forth in the TNC, in particular:

  • Gross Calorific Value ranging from 11.177 kWh/m3 (40.237 MJ/m3) to 12.618 kWh/ m3 (45.424 MJ/m3)


Conversion factors for recalculating the quantity of natural gas expressed in volumetric units (Nm3) and the quantity of liquefied natural gas (LNG) expressed in volumetric units (m3LNG) into gas quantity expressed in energy units (kWh) calculated as an arithmetic mean of the heat of combustion of light and heavy gas according to LNG quality parameters applicable at the LNG Terminal in Świnoujście, assume the following values:

  1. kWh/Nm3 = 11,897
  2. MWh/m3LNG=  6,86

List of companies authorised to act as a Surveyor at the LNG Terminal

List of companies authorised to act as a Surveyor at the LNG Terminal:

  • Intertek
  • Saybolt
  • SGS

  • Actual quantity of unloaded LNG/truckloaded LNG
  • Public information on hazards, emergency prevention and rescue procedures at the LNG Terminal
  • Share

    Share

    • X
    • LinkedIn
    • Email
    • Bluesky
    Kopiuj
  • Eksport to PDF
  • Print page
  • Site map
  • Data transparency
  • GDPR
  • Cookies policy
  • Contact
Our website uses cookies

To ensure security and improve service quality, the website you visit uses cookie files.
If you do not agree to the use of cookies, please change your browser settings or leave the website.

Cookies policy