Construction of the Gustorzyn-Wronów gas pipeline commences
In November this year, GAZ-SYSTEM concluded the first agreement with the contractor for the construction of the gas pipeline section that runs from Rawa Mazowiecka to Wronów. At the same time, as part of investor deliveries, the company concluded a contract for the supply of pipes, which will be used, among others, for the implementation of this project.The entire Gustorzyn - Wronów gas pipeline with a length of 308 km will increase security and continuity of gas supply to consumers in central Poland. Its task is to connect the hub and gas compressor station under construction in Gustorzyn with the hub and compressor station in Wronowo. The implementation of this investment is divided into three stages:- stage I Gustorzyn - Leśniewice with the length of 54 km;
- stage II Leśniewice - Rawa Mazowiecka with the length of 100 km;
- stage III Rawa Mazowiecka - Wronów with the length of 154 km.